Henan New Electric Power Delivers 33 Oil-Immersed Transformers & 60 VCBs
Project Date: October 22, 2026
Destination: Madagascar, Africa
Equipment Supplied:
- 33 Units Three-Phase Hermetically Sealed Oil-Immersed Transformers (100 kVA – 1600 kVA, 20 kV / 400 V)
- 60 Units Medium-Voltage Indoor/Outdoor Vacuum Circuit Breakers (VCBs)


1. Project Overview & Client Requirements
To support the ongoing regional grid upgrading and commercial power distribution projects in Madagascar, the client required a reliable, climate-resilient medium-voltage power package. Key project requirements included:
- Non-Standard Grid Voltage: Step-down conversion from 20 kV transmission to 400 V / 230 V utilization voltage.
- Multi-Capacity Scalability: Batch configuration ranging from decentralized 100 kVA distribution units up to centralized 1600 kVA industrial capacities.
- Harsh Tropical Environment: High humidity, coastal salinity, and seasonal high ambient temperatures.
- Integrated Switching & Protection: Coordinated high-reliability Vacuum Circuit Breakers (VCBs) to ensure instantaneous arc extinguishing and short-circuit protection.


2. Engineering Solutions & Customized Advantages
- Hermetically Sealed Tank & Low Loss: The oil-immersed transformers utilize high-permeability cold-rolled silicon steel cores and high-grade transformer oil, offering low no-load losses, zero maintenance, and IP-rated junction enclosures to resist moisture and dust.
- Strict Compliance with IEC Standards: Fully manufactured and factory-tested per IEC 60076 (Transformers) and IEC 62271-100 (Switchgear), guaranteeing dielectric withstand and thermal stability.
- Heavy-Duty Export Packaging: All 33 transformers and 60 circuit breakers were secured in reinforced, sea-freight wooden crates with desiccant protection to prevent corrosion and mechanical shock during cross-ocean transit.
3. Factory Testing & Night Dispatch
After passing full routine testing (ratio, insulation resistance, winding resistance, and temperature rise checks), the entire batch completed packaging and night loading on October 22, ready for shipping to Toamasina Port, Madagascar.